The rebuilding of the Dimitris

You are here: Home > The yachts

News by date

As the Dimitris will be used for liveaboard rather than for vacation trips, some things are rather unpractical in the current configuration.

For that reason, we have chosen to have some of the cabins rebuilt before we depart from Greece. The Greeks are known as excellent carpenters.

As the rebuild includes moving a watertight bulkhead 60cm, and rearranging some internal walls, we have contracted with an experienced ships designer/constructor/rebuilder who btw. also was the original maintainer of the vessel for the previous owner.

The following is approximately the layout of the Dimitris before the rebuild:

The following shows how the arrangement is after the rebuild (approx.):

There will be made an additional temporary, but supposedly comfortable, bunk in the aft, port side cabin, which cant be seen on the picture. It will be available for one of the crew members.

The rebuild has been planned after many considerations regarding the ships construction. The strength of the vessel is the same after the rebuild as before, and as we keep the water tight bulkhead in the front, its still safe in case of a breach of the front part of the full in case of collision etc.

The front 'captains' cabin will loose its toilet and shower, but the 2 bunks will remain. It will later on be used for storage and optionally guest space.

The two main cabins in the forward section, will be collapsed into one, and the area taken up by the captains toilet/shower area, will be added to the room, to make a big master bedroom.

The master bedroom will also contain a table, and a washer and a dryer in addition to drawers and shelves for storage.

One toilet will be ripped totally down, except for the outer walls. It will be used as a wardrobe.

The other toilet will be heavily extended in both directions, and an electric toilet with full size bowl will be installed. In addition a seperate shower cabin is installed. The floor may be lowered somewhat to provide better headroom.

The aft port side cabin, will be changed from a double bed to a single bed, and a small table and shelfs added. For the sailing to Denmark, there will be installed a temporary, but supposedly comfortable, bunk.

July 12 2006.

Please from today follow the rebuild on the diary page here.

July 5 2006.

Today more news has come from the contractors.

June 30 2006.

Today Ive received detailed info about changes and what they are looking at.

As all the interiour incl. walls, floors and roofing, has been removed in front of the mast, a thorough inspection of seacocks, tubings, water tanks, mast foot, electric wires, anode grounds and the hull itself could be made.

They are working around the clock to keep up with schedule.

 

The following pictures shows the progress of the rebuild... warning... scary ;)


Dimitris original layout

Dimitris new layout

Front section cabin dismantling

Front section cabins being dismantled

Wall between front section cabins removed.

Water tanks in front section cabins being removed

Old bulkhead to captains toilet being removed.

Old bulkhead to captains toilet removed.

Old bulkhead to captains toilet removed.

View from port mastercabin toilet to front cabin